UNTINGTON LAKE INFORMATION
SUMMER AND WINTER POOL ELEVATIONS
BASIN PROJECTS SUMMER WINTER REFILL DATE DRAWDOWN DATE
Muskingum Atwood 928.0
922.5 1 February 1 November
Charles Mill 997.0
993.0 1 February 1 December
Clendening
898.0 893.0 1 February 15 November
Dillon
737.0 734.0 1 April 1 November
Leesville
963.0 957.0 1 February 15 November
Piedmont
913.0 909.0 1 February 15 November
Pleasant Hill 1020.0
1014.0 1 February 1 December
Senecaville 832.2
828.2 1 February 15 November
Tappan
899.3 895.0 1 February 1 November
Scioto Alum Creek 888.0 885.0
1 April 1 October
Deer Creek
810.0 796.0 1 April Mid October
Delaware
915.0 910.0 1 April 1 November
Paint Creek 798.0
787.5 1 April Mid October
Kanawha Bluestone 1410.0 1406.0
1 April 27 November
Summersville 1652.0
1575.0 1 April In September
Sutton
922.0 895.0 1 April 1 October
Drawdown at Summersville usually begins with the first Friday after Labor Day in conjunction with whitewater season.
Starting dates can vary also if hydrologic conditions warrant an earlier starting date such as dry fall and winter.
The above information was provided on 08/16/99
by Victor L Pratt, Victorp (AT) Lrh.usace.army.mil
at the Huntington District of the US Army Corps of Engineers.
Alternate contact information:
Victor Pratt, 304.399.5173, WatInfo (AT) lrh01.usace.army.mil